Construction Alerts
The following is a list of the major active construction projects in the City that have an impact on daily traffic. Projects are listed in the following, by the primary street that is impacted. To find out more details regarding work on a specific street, including construction schedules, select the street name and the field will expand to show additional information.
Please note that the completion dates listed in the following are approximate dates, based on schedules provided to the City by the contractors/developers for each project. Unexpected field conditions, inclement weather, and other unforeseen circumstances may impact schedules.
Please check this site for regular updates.
For questions, please email the Public Works/Engineering Department or call 951-677-7751, ext. 5.
City Construction Projects
- Project: Bundy Canyon Road Improvement Project (Segment 1)
- Project Number : CIP 026-1
- Project Type: City Capital Improvement Project
- Project Updates
UPDATE 9/7/23
The City’s Pavement Rehabilitation Project is now under construction. As part of this year’s project, crack fill improvements are underway on over 120 streets in the City. The attached exhibit shows streets included in this year’s project. During the crack fill process, No Parking signs will be posted a minimum of 48 hours prior to crews scheduling their work. Once signs are removed from construction cones, on-street parking is permitted. Streets will remain accessible for residents, through traffic, waste pickup, and mail deliveries during this stage. Please drive carefully through construction areas and observe all posted signs posted during this process.
Slurry Seal is currently planned in several residential neighborhoods throughout the City from October 16th through Nov 3rd . Notices have been delivered to residents who will be impacted by the contractor’s operations. Anticipate slurry resurfacing to occur 5-6 weeks after streets have been crack filled.
Citywide, improvements to several concrete ADA ramps, cross-gutters, and other drainage structures have been included within this year's project.
Questions may be addressed to the City Project Manager Mr. Cameron Luna at 951-677-7751 x245 or cluna@cityofwildomar.org. Thank you for your cooperation.
- Project: Road Maintenance and Rehabilitation Project & Slurry Seal Project
- Project Number : CIP 057-2, CIP 058-2
- Project Type: City Capital Improvement Project
- Project Manager: Cameron Luna, email: cluna@cityofwildomar.org, phone: 951 677-7751x245
- Contractor: All American Asphalt
- Fiscal Impact: $3,793,100.56
- Duration: 150 Working Days, August 2023 - February 2024
- Description of Work: Removal and Pulverization of existing asphalt concrete pavement and aggregate base, reconstruct PCC ramps, Modify drainage inlets and crossings; Perform Crack Seal, ARAM surfacing, Asphalt surfacing, ARHM surfacing, and Type Il PME-RAP Slurry Seal; Reinstall pavement markings, striping, and traffic loops; Adjust utility manholes and valves to grade.
- Locations: See Exhibit
Developer Construction Projects
Please note that the completion dates listed in the following are approximate dates, based on schedules provided to the City by the contractors/developers for each project. Unexpected field conditions, inclement weather, and other unforeseen circumstances may impact schedules.
Update (July 12, 2023):
- Ongoing @ Vertical build
Update (January 26, 2023):
- Backbone dry utility installation and backfill on Elizabeth Lane completed.
- Onsite dry utility backbone installation will be completed approximately January 27, 2023
- Work Order 1 (phases Models, 1-3 onsite) curb and gutter and streets paved approximately January 31, 2023.
- Model homes will be complete February 17, 2023
- Model grand opening February 25, 2023
- Phase 1 Production Homes to start onsite trenching on February 10, 2023
Please see 'Overall Project Schedule' below for additional details.Update (January 10, 2023):
- On hold due to rain event.
Update (January 3, 2023):
- On hold due to rain event.
Update (December 27, 2022):
- On hold due to rain event.
Update (December 12, 2022):
- Elizabeth Lane is currently under construction.
- Onsite streets are almost complete.
- Model homes are under construction.
- Production units have started construction.
Update (November 23, 2022):
- No change in updates.
Update (October 28, 2022):
- Prielipp construction is complete and is fully open to through traffic.
- Improvements on Elizabeth Lane are in progress.
Update (September 30, 2022):
- Prielipp construction is still underway. Base paving and compaction are complete. Procurement of AC and concrete has delayed completion again, due to supply chain issues. We sincerely apologize for the inconvenience, and are working onsite with the developer and their contractor to assist however we can so the construction can be completed as quickly as possible, and the road reopened to through traffic.
Update (September 22, 2022):
- Prielipp construction is underway. Completion still expected the week of 9/30, pending no additional field issues.
Update (September 15, 2022):
- Headwall for storm drain facilities currently under construction.
- Prielipp widening and improvements expected to begin in the next few weeks.
Update (September 7, 2022):
- No new updates.
Update (August 31, 2022):
- Contractor will be working on fire hydrant tie-ins.
- Curb and gutter staking for Prielipp and Elizabeth will be installed.
- Construction of curb and gutter will be followed by street improvements.
Update (August 25, 2022)
- No new updates. Project schedule updated on 8/17/22 is still current.
Update (August 17, 2022)
- All storm drain in Prielipp Road has been constructed.
- Relocation of fire hydrants along Prielipp is underway.
- Domestic water construction in Elizabeth Lane is underway.
- Wet utilities at the Prielipp and Elizabeth Lane intersection are complete.
- Headwall/retaining wall for drainage outlet structure along Prielipp is scheduled for construction within the next two weeks.
- After completion of headwall/retaining wall, paving/widening on Prielipp can commence.
Update (July 22, 2022):
- All in-tract sewer proposed completion early next week.
- Water line construction set to begin next week.
- Dry utility construction will begin at the end of August.
- In-tract curb and gutter construction will begin next week.
- Contractor will begin recertifying all pads due to erosion.
Overall Project Schedule (Updated on September 30, 2022)
Update (July 12, 2023):
- Ongoing with Box Culvert, Pouring Concrete 7/13/23 for Last Cells Apron and Slope @ N/W corner
- Curb and Gutter on McVicar 8/7/23
- Paving Grand Avenue 7/24/23
- Construction will require the intermittent closure of bicycle facilities and one lane of through traffic. The public should be aware of flaggers directing traffic on either end of the work zone during this period. Traffic on grand will be via a single lane with flaggers controlling traffic in each direction. In addition, Grand Avenue will have a reduced speed limit through the work zone during construction. Please exercise caution and follow all traffic control signage at all times and especially during this work period. We appreciate the public’s patience while these construction activities are conducted.
Update (June 14, 2023):
- Grand Avenue between Claremont Street and Willow Bay Road will have construction activity during daytime hours for the next two months.
Construction will require the intermittent closure of bicycle facilities and one lane of through traffic. The public should be aware of flaggers directing traffic on either end of the work zone during this period. Traffic on grand will be via a single lane with flaggers controlling traffic in each direction. In addition, Grand Avenue will have a reduced speed limit through the work zone during construction. Please exercise caution and follow all traffic control signage at all times and especially during this work period. We appreciate the public’s patience while these construction activities are conducted.
Update (January 26, 2023):
- Offsite Improvements
- January 30, 2023 (tentative) - Culvert starts, depending on how wet it is.
- February 10, 2023 - Rule 20 on Grand Avenue, SCE to have energized from overhead to underground.
- 2/27/1023 - Start grading street shoulder for paving, on Grand Avenue
- In Tract work
- Phases 3-5 under construction.
- Phase 6 - Start February 6, 2023.
- Please see the following 'Overall Project Schedule' for additional details.
Update (January 10, 2023):
- On hold due to rain event.
Update (January 3, 2023):
- On hold due to rain event.
Update (December 27, 2022):
- On hold due to rain event.
Update (December 12, 2022):
- No change in updates.
Update (November 23, 2022):
- No change in updates.
Update (October 28, 2022):
- Construction of improvements on McVicar between Grand and Whispering Way are complete.
- SCE facilities in Grand are in the process of being relocated.
- Construction of improvements on Grand has commenced within the area that is already closed to through traffic.
Update (September 15, 2022):
- Partial re-opening of McVicar Street from Whispering Way to Grand Avenue
- Curb and Gutter on Grand is 50% complete.
- No updates on the project schedule.
Update (September 7, 2022):
- Off Tract Improvements
- Grand Avenue - pouring curb and gutter
- McVicar Street from Grand Avenue to Whispering Way - street improvement work
- No updates on the project schedule.
Update (September 1, 2022):
- No new updates. The following Project Schedule has been updated.
Update (August 24, 2022):
- Edison de-energizing facilities at culvert: a portion has been de-energize, waiting for a portion with street light facilities and facilities running under culvert. ETA for this is September 30, 2022.
- The goal is to have McVicar 100% open and paved completely over culvert by February 28, 2023.
Update (August 17, 2022):
- Construction of storm drain connections at the intersection of Grand and McVicar is in progress and should be completed by the end of the week.
- McVicar utilities are complete, with the exception of the RCFC box culvert (master planned facilities), and is now base paved with curb and gutter almost complete.
- Curb and gutter is being constructed on Grand, and relocation of SCE poles will soon follow.
Update (July 22, 2022):
- Working on Storm Drain in McVicar in coordination with RCFC in field. Projected start of construction for box culvert, at the end of August.
- BMPs, graffiti, and traffic control was in disarray - everything has been cleaned up as of today.
- Traffic Control on McVicar has been updated per City Traffic Engineer's request.
Overall Project Schedule (Updated September 1, 2022)
Update (July 12, 2023):
- Ongoing Vertical Build
- Ongoing Wet utilities
- Paving Wildomar Trail 7/17-7/19
- Caltrans Guardrail 7/20-7/26
- 7/24 - 8/4 Sewer connection along Wildomar Trail Pending Edison *
- AC Berm 7/24 *
- Energizing Signal 7/27
- Sign and Striping 7/24 TBD
Update (June 14, 2023):
- Southern California Edison (SCE) will be upgrading facilities for the Baxter Village project today and tomorrow, starting at 9AM. Traffic control will consist of split lane traffic with flaggers, and the signal at Cervera and Wildomar Trail will be set to flash.
Update (January 26, 2023):
- Working on transitional paving from the old Wildomar Trail to the new road this week. A portion of the new road will be completed and striped for use by 1/27.
- Baxter Road will be closed from 1/26 though March to construct infrastructure and new roads (Margaret Lane and Baxter Road).
- Message boards have been updated to reflect the new closures, and flag-men are in place and at the ready.
Please see the following 'Overall Project Schedule' for additional details.
Update (January 10, 2023):
- On hold due to rain event.
Update (January 3, 2023):
- On hold due to rain event.
Update (December 27, 2022):
- On hold due to rain event.
Update (December 12, 2022):
- Wildomar Trail widening is in process.
Update (November 23, 2022):
- No change in updates.
Update (October 28, 2022):
- Utilities across Wildomar Trail are complete.
- Wildomar Trail street widening has commenced.
Update (September 15, 2022):
- Installation of utility laterals across Wildomar Trail.
Update (8/31, September 1, 2022):
- No updates at this time.
Update (August 25, 2022):
- First phase of new road paving is projected to begin on September 13, 2022.
- First phase of Wildomar road crossing of wet utilities to be completed by August 26, 2022.
- Contractor might need a day or two of lane closures during the week of 9/6 for dry utilities (landscape sleeves, traffic, street light conduits and communication cables.
- Contractor will be making lane changes the week of 9/13 during paving operations per traffic control plans.
Update (August 17, 2022):
- Water and storm drain line construction with traffic crossing Wildomar Trail scheduled for 8/18 through 8/30.
- First section of paving on Wildomar Trail is scheduled to begin on or around September 13, 2022.
Update (July 22, 2022):
- Sewer and water line work across Wildomar Trail will begin next Tuesday through 7/26-Wednesday, 7/27 during the hours of 9 am-2 pm. Sewer will begin first.
- Road depression at project truck crossing will be fixed at the same time.
- All work will utilize the existing lane closure with flagmen and traffic control.
- Traffic plates will be anchored and welded for safety and will remain in place until the new road witches over.
- Waterline construction is scheduled to commence after sewer is complete.
Overall Project Schedule (No change from August 18, 2022)
Update (January 10, 2023):
- On hold due to rain event.
- Please see the following 'Overall Project Schedule' for additional details.
Update (January 3, 2023):
- On hold due to rain event.
Update (December 27, 2022):
- On hold due to rain event.
Update (December 12, 2022):
- No new updates.
Update (November 23, 2022):
- Production phases have started construction.
Update (October 28, 2022):
- Interior streets are paved.
- Models have been constructed.
Update (September 15, 2022):
- No new updates.
Update (September 7, 2022):
- No new updates.
Update (August 31, 2022):
- No new updates. The following Project Schedule has been updated.
Update (August 24, 2022):
- No new updates. The following Project Schedule has been updated with completed work.
Update (August 17, 2022):
- Construction of shoulder improvements on Summer Sage Way are nearing completion.
- In-tract sewer, water, and storm drain are currently under construction.
Overall Project Schedule (Updated on August 31, 2022)
Update (July 12, 2023):
- Ongoing Vertical Build - 4/7 stories complete
- Ongoing Wet utilities
- No new updates.
Please see 'Overall Project Schedule' in the following for additional details.
Update (January 3, 2023):
- No new updates
Update (December 27, 2022):
- No new updates
Update (December 12, 2022):
- No new updates
Update (September 15, 2022):
- No new updates.
Update (August 29, 2022):
- The temporary parking lot at Yamas and Prielipp will no have any road closures associated with the work.
- 2nd approach was poured on August 24, 2022 since material was released early.
- Site work was scheduled to be completed Friday 8/25 and the project will be turned over for use.
Update (August 18, 2022):
- DPR Construction-directed work is all occurring on-site at the Inland Valley Medical Center campus.
- Ongoing activities are mainly grading activities, with various underground utility work ongoing and some of the temporary infrastructure work for the buildings (under HCAI permits).
- It has been reported that the temporary parking lot at Prielipp and Yamas is scheduled for completion by the end of August.