Construction Alerts

The following is a list of the major active construction projects in the City that have an impact on daily traffic. Projects are listed in the following, by the primary street that is impacted. To find out more details regarding work on a specific street, including construction schedules, select the street name and the field will expand to show additional information.

Please note that the completion dates listed in the following are approximate dates, based on schedules provided to the City by the contractors/developers for each project. Unexpected field conditions, inclement weather, and other unforeseen circumstances may impact schedules.

Please check this site for regular updates.

For questions, please email the Public Works/Engineering Department or call 951-677-7751, ext. 5.

City Construction Projects

  1. Bundy Canyon Road
  • Project: Bundy Canyon Road Improvement Project (Segment 1)
  • Project Number : CIP 026-1
  • Project Type: City Capital Improvement Project
  • Project Updates
  1. CITYWIDE rOAD rEHABILITATION AND SLURRY SEAL PROJECT

Developer Construction Projects

Please note that the completion dates listed in the following are approximate dates, based on schedules provided to the City by the contractors/developers for each project. Unexpected field conditions, inclement weather, and other unforeseen circumstances may impact schedules.

  1. Lennar Homes - Horizons

Horizons Map

Update (July 12, 2023):

  • Ongoing @ Vertical build 

Update (January 26, 2023):

  • Backbone dry utility installation and backfill on Elizabeth Lane completed.
  • Onsite dry utility backbone installation will be completed approximately January 27, 2023
  • Work Order 1 (phases Models, 1-3 onsite) curb and gutter and streets paved approximately January 31, 2023.
  • Model homes will be complete February 17, 2023
  • Model grand opening February 25, 2023
  • Phase 1 Production Homes to start onsite trenching on February 10, 2023

Please see 'Overall Project Schedule' below for additional details.Update (January 10, 2023):

  • On hold due to rain event.

Update (January 3, 2023):

  • On hold due to rain event.

Update (December 27, 2022):

  • On hold due to rain event.

Update (December 12, 2022):

  • Elizabeth Lane is currently under construction.
  • Onsite streets are almost complete.
  • Model homes are under construction.
  • Production units have started construction.

Update (November 23, 2022):

  • No change in updates.

Update (October 28, 2022):

  • Prielipp construction is complete and is fully open to through traffic.
  • Improvements on Elizabeth Lane are in progress.

Update (September 30, 2022):

  • Prielipp construction is still underway. Base paving and compaction are complete. Procurement of AC and concrete has delayed completion again, due to supply chain issues. We sincerely apologize for the inconvenience, and are working onsite with the developer and their contractor to assist however we can so the construction can be completed as quickly as possible, and the road reopened to through traffic.

Update (September 22, 2022):

  • Prielipp construction is underway. Completion still expected the week of 9/30, pending no additional field issues.

Update (September 15, 2022):

  • Headwall for storm drain facilities currently under construction.
  • Prielipp widening and improvements expected to begin in the next few weeks.

Update (September 7, 2022):

  • No new updates.

Update (August 31, 2022):

  • Contractor will be working on fire hydrant tie-ins.
  • Curb and gutter staking for Prielipp and Elizabeth will be installed.
  • Construction of curb and gutter will be followed by street improvements.

Update (August 25, 2022)

  • No new updates. Project schedule updated on 8/17/22 is still current.

Update (August 17, 2022)

  • All storm drain in Prielipp Road has been constructed.
  • Relocation of fire hydrants along Prielipp is underway.
  • Domestic water construction in Elizabeth Lane is underway.
  • Wet utilities at the Prielipp and Elizabeth Lane intersection are complete.
  • Headwall/retaining wall for drainage outlet structure along Prielipp is scheduled for construction within the next two weeks.
  • After completion of headwall/retaining wall, paving/widening on Prielipp can commence.

Update (July 22, 2022):

  • All in-tract sewer proposed completion early next week.
  • Water line construction set to begin next week.
  • Dry utility construction will begin at the end of August.
  • In-tract curb and gutter construction will begin next week.
  • Contractor will begin recertifying all pads due to erosion.

Overall Lennar Homes - Horizons Project ScheduleOverall Project Schedule (Updated on September 30, 2022)

  1. Beazer Homes, Boulder Creek
  1. Baxter Village
  1. KB Homes - Verano
  1. IVMC Expansion Project

Other Construction Alerts